'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months

Main News Image

Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.

"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."

Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.

mediabaaji add

Related News

60.1 million collected in reconstruction fund

Kathmandu. So far, 60 million rupees have been collected in the physical infrastructure reconstruction fund established by the government for the reconstruction of physical structures damaged by arson and vandalism dur...

Foreign currency exchange rates for today published

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to Rashtra Bank, the buying rate of one US dollar has been fixed at 150 rupees 74 paisa and the selling rate has been fixed at 151 rupees 34 pai...

The price of gas has dropped in Kathmandu, now at Rs 2,600 per cylinder

Kathmandu. Nepal LP Gas Industry Association has requested the gas industry and sellers not to take the price of gas in Kathmandu valley more than 2000 rupees per cylinder. Through the notice issued by the association on Thursday, the corporation...

The decision of the Water Industry Federation to increase the price of drinking water

Kathmandu. Nepal Water Industry Federation has decided to increase the price of treated drinking water. According to the federation, the increase in the price of raw materials and the increase in transportation costs have made it impossible to ope...

The price of gold increased on Tuesday, now how much per tola?

Kathmandu. The price of gold has increased in Nepali market today. Gold tola has gone up by 1 thousand 600 rupees. According to the Nepal Gold and Silver Traders Federation, today gold is being bought and sold at 3 lakh 1 thousand 300 rupees per t...

Chandragiri Investment Group will issue 'IPO' shares

Kathmandu. Chandragiri Investment Group Limited is going to issue a primary share IPO for ordinary citizens.  The company's first general meeting held today passed the proposal to issue the IPO. The authorized capital of the company is Rs 50...