'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months

Main News Image

Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.

"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."

Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.

mediabaaji add

Related News

The Electricity Authority will provide employment to eight more people from the Shaheed family

Kathmandu. The Nepal Electricity Authority has decided to provide employment to eight more family members who were martyred during the Genji movement. Chairman of the Board of Directors and Minister of Energy, Water Resources and Irrigation Virajb...

An increase of 4.59 points in NEPSE, the turnover is 4.9 billion

Kathmandu. On the fifth or last trading day of the week, NEPSE index increased by 4.59 points to 2640.54. During the day, 104 million 31 thousand 760 shares of 328 companies were bought and sold, resulting in a turnover of 4 billion 908 million sh...

Double-digit growth in NEPSE, turnover limited to 3 billion 29 million

Kathmandu. On the second trading day of the week, the NEPSE index increased by 16.37 points to 2619.99. During the day, 78 lakh 4 thousand 45 shares of 325 companies were bought and sold, and 3 billion 294 million shar...

Friday's exchange rate: Kuwaiti dinar is the most expensive, which currency is worth?

Kathmandu. Nepal Rastra Bank has announced the new exchange rate of foreign currency for Friday, February 8. According to the new rate set by the bank, the price of the US dollar has increased today and the buying rate of one dollar has remained a...

This is the foreign exchange rate

The Kathmandu. Nepal Rastra Bank has fixed the exchange rate of foreign currency for today. According to the National Bank, the buying rate of US dollar has been fixed at 152 rupees 31 paise and selling rate at 152 rupees 91 paise. The Australian...

Study report of Kerung-Kathmandu railway line prepared

Kathmandu. The Chinese side is going to submit the feasibility study report of the long-awaited Kathmandu-Kerung inland electric railway connecting Nepal and China within the next one and a half months. In a presentation held at the Ministry of Ph...