'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
Gold prices fell modestly, while silver rose
Kathmandu. On Thursday, the price of gold in the Nepalese market has decreased. According to the Federation of Nepal Gold and Silver Traders, today the price of gold has decreased by Rs 100 per tola to Rs 3 lakh 6 thousand 500 per tola. Earlier on...
Citizens Super 30 Mutual Fund will give a cash return of 5.25%, when will the book close?
Kathmandu. Citizens Super 30 Mutual Fund, operated under Citizens Mutual Fund, is going to give 5.25 percent cash return to the unit holders for the financial year 2082 and 83.
The unit owner registration book will be closed for one day on O...
Modi Energy has received preliminary approval for the issue of rights shares from the Electricity Regulatory Commission
Kathmandu. Modi Energy Limited has received prior approval from the Electricity Regulatory Commission to issue rights shares. The company had submitted an application to the Electricity Regulatory Commission seeking prior approval for the issue of...
Authority constructing new Butwal Lamhi transmission line
Kathmandu. The Nepal Electricity Authority is going to construct a new Butwal Lamahi power transmission line with a capacity of 400 KV. The total length of 161 km transmission line is intended to transmit the electricity of eastern Nepal to the we...
Today, the price of gold increased by Rs 300 per tola
Kathmandu. Today, the price of gold in the Nepalese market has increased by Rs 300 per tola, while silver has increased by Rs 5 per tola. According to the Federation of Nepal Gold and Silver Dealers, today the price of printed gold has been fixed...
NEPSE fell by 12.58 points, trading fell to 8 billion 63 crores
Kathmandu. On the third trading day of the week, NEPSE index decreased by 12.58 points and remained at the point of 2683.15. During the day, 187.03 thousand 183 shares of 322 companies were bought and sold, and 8.63 billion 1.5 million shares were...