'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months

Main News Image

Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.

"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."

Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.

mediabaaji add

Related News

The price of petroleum products fell!

Kathmandu. Nepal Oil Corporation has adjusted the price of petroleum products. The corporation has reduced the price of petrol by three rupees per liter with effect from 12:00 pm. Similarly, diesel and kerosene per liter has decreased by one rupee...

Palpa Cement will issue an IPO for the general public from February 12

Kathmandu. Palpa Cement Industries Limited is going to issue an IPO to the general public from the 12th of February. In the first phase, the company has issued and distributed IPO to local residents of industry-affected areas and Nepalese working...

Exchange rate, dollar and euro value stable

Kathmandu. Nepal Rastra Bank has announced the official exchange rate of foreign currency for Saturday. According to the updated information published by the Central Bank, the buying rate of one US dollar has been fixed at 151 rupees 62 paisa and...

The price of gold increased, how much per tola on Thursday?

Kathmandu. The price of gold has increased in Nepali market today. Gold tola has gone up by 800 rupees. According to the Nepal Gold and Silver Traders Federation, gold is being traded at 284,000 rupees per tola today. The price of 10 grams of gold...

Kimathanka Arun hydropower project will be built with indigenous capital, investment modality decided

Kathmandu. The investment modality has been decided to build the Kimathanka Arun semi-reservoir hydropower project with a capacity of 454 MW identified in Bhotkhola rural municipality-2 of Sankhuwasabha with indigenous capital. The estimated cost...

The price of gold increased suddenly, now how much per tola?

Kathmandu. The price of gold has increased in Nepali market today. At the mouth of Haritalika Tij, gold has increased by 1000 200 rupees. According to the Federation of Nepal Gold and Silver Traders, today the price of gold has remained at Rs 3 la...