'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
The new exchange rate of foreign currency was determined, what is the price of which country?
Kathmandu. Nepal Rastra Bank has determined the foreign currency exchange rate for today. According to the new rate announced by the Central Bank, the buying rate of one US dollar is set at 153 rupees 10 paisa and the selling rate is 153 rupees 70...
NEPSE index decreased by 25.81 points, how much is the transaction amount?
Kathmandu. On Wednesday, the stock market gauge NEPSE index fell. Today, NEPSE index decreased by 25.81 points and reached 2744.45 points. A total of 1 crore 21 lakh 34 thousand 360 shares of 351 companies were bought and sold in NEPSE, and over R...
Preparation of price adjustment to prevent shortage of essential medicines, demand for automated system
Kathmandu. The government has started the price adjustment process to solve the frequent shortage of essential medicines. Due to the lack of price review for a long time, the supply of some life-saving medicines in the market is being affected due...
Share Hub conducts technical analysis training for beginner investors, how to join?
Kathmandu. Share Hub is going to conduct a 10-day online training aimed at beginner investors who want to learn technical analysis in the stock market. Technical Analysis Training for Beginners will teach you how to understand price charts,...
Five construction companies blacklisted, barred from participating in any public procurement
Kathmandu. The Public Procurement Monitoring Office has blacklisted five construction companies. The office issued a notice today and said that the company has been blacklisted.
According to the written submissions from various agencies, acc...
The price of one tola of gold is three lakh eighteen thousand eight hundred
Kathmandu. Even today, the price of gold and silver has set a record in the local market. According to the Federation of Nepal Gold and Silver Traders, today the price of one tola of printed gold is 318 thousand 800 and the value of silver is 7 th...