'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months

Main News Image

Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.

"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."

Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.

mediabaaji add

Related News

Study report of Kerung-Kathmandu railway line prepared

Kathmandu. The Chinese side is going to submit the feasibility study report of the long-awaited Kathmandu-Kerung inland electric railway connecting Nepal and China within the next one and a half months. In a presentation held at the Ministry of Ph...

The euro and pound fell, while the Australian dollar and Bahraini dinar rose

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currencies for Friday. Today, while the exchange rate of the US dollar and the Kuwaiti dinar remained stable, currencies including the Bahraini dinar and the Australian dolla...

Exchange rate: The price of dollar, euro and pound has increased, which currency is being bought and sold in how much?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for Sunday. According to the fixed exchange rate, the buying rate of one US dollar is 151 rupees 56 paisa and the selling rate is 152 rupees 16 paisa.

Similarl...

NEPSE decreased by 37.63 points throughout the week, how much is the transaction on which day?

Kathmandu. This week, NEPSE index decreased by 37.63 points and reached 2671.07 points. NEPSE, which closed last week at 2708.70 points, decreased by 37.63 points to 2671.07 points this week. The market was open on all five trading days this week....

61.62 percent of rice planting has been completed across the country, the progress is slower than last year

Kathmandu. In the current fiscal year 2083, 84, 61.62 percent of rice planting has been completed across the country so far. According to the latest data of the Ministry of Agriculture and Livestock Development, out of the total 13 lakh 66 thousan...

The price of gold increased, how much is the transaction?

Kathmandu. The price of gold and silver has increased in the local market today. Compared to Monday, the price of both metals increased. According to the Federation of Nepal Gold and Silver Traders, today the price of one tola of gold is 290 thous...