'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
Nepal's emphasis on strengthening the United Nations development system
Kathmandu. Nepal has emphasized on the need to strengthen the United Nations development system. Nepal is of the opinion that it is necessary to do so to ensure multilateralism. Lok Bahadur Thapa, Permanent Representative of Nepal to the United Na...
Today is the last day to file for Everest Color's IPO
Kathmandu. Today is the last day to apply for the IPO that Everest Color Limited is issuing to the general public from June 22. In the first phase, IPOs are distributed to Nepalis who are employed abroad and in the second phase, IPOs are being iss...
Fuel prices have increased from India, but will not increase immediately in Nepal
Kathmandu. Indian Oil Corporation IOC has increased the price of petroleum products sold to Nepal. According to the new price list sent by IOC to Nepal Oil Corporation on Wednesday, petrol per liter has increased by Rs 20.44 paise, diesel by Rs. S...
Fall in the price of gold, now how much per tola?
Kathmandu. The price of gold has decreased in Nepali market today. Gold tola has fallen by 1 thousand 400 rupees. According to the Nepal Gold and Silver Traders Federation, gold is being bought and sold at Rs 2 lakh 84 thousand 400 per tola today....
Foreign Currency Exchange Rates: The value of the Euro and Pound fluctuates with the US Dollar
Kathmandu. According to the foreign currency exchange rate determined by Nepal Rastra Bank for today, the buying rate of one US dollar has remained at 150 rupees 88 paise and the selling rate has been maintained at 151 rupees 48 paise. While the b...
Fourth extension of Pokhara-Muglin road project
Kaski. Pokhara-Muglin road upgrading project has been extended for the fourth time. After the deadline extended for the third time has passed, the project has been given the final deadline till the 10th of November.
According to Krishna Baha...