'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
High increase in the price of gold, now how much per tola?
Kathmandu. The price of gold has increased in Nepali market today. Gold rose by Rs 6,200 per tola in one day. According to the Nepal Gold and Silver Traders Federation, gold is being bought and sold at Rs 2 lakh 83 thousand 500 per tola today. On...
Government's relief package: Rasuwa flood victims will get up to 50% advance insurance claim payment
Kathmandu. The government has decided to provide advance payment to the insured affected by the Rasuwa flood based on the preliminary assessment of insurance claims. This arrangement has been made through the 'Rasuwa flood recovery package' announ...
What is the exchange rate of which foreign currency on Wednesday?
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the determined exchange rate, the buying rate of one US dollar is 144 rupees 78 paisa and the selling rate is 145 rupees 38 paisa. Similarly,...
1.5 lakh shares of Muktinath Development Bank for sale at Rs 135 per share
Kathmandu. Muktinath Bikas Bank Limited has put founder shares on sale. The bank has put 1 lakh 56 thousand 283 shares for sale towards the founder group.
For the purchase of the said shares, any person or company should apply to the office...
Rastra Bank will collect 1 trillion 25 billion deposits today, more liquidity in the market
Kathmandu. Nepal Rastra Bank is going to collect deposits worth one trillion 25 billion rupees again this Friday to manage excess liquidity in the financial system. Even after two weeks of formation of the new government, since the liquidity press...
The value of the Japanese yen has fallen, see foreign currency exchange rates
Kathmandu. The value of the Japanese yen has fallen somewhat. The buying rate of 10 yen has reached 9 rupees 48 paisa and the selling rate has reached 9 rupees 52 paisa.
According to Nepal Rastra Bank's foreign currency exchange rate for tod...