'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months

Main News Image

Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.

"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."

Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.

mediabaaji add

Related News

A decline of 22.33 points in NEPSE, the turnover fell to 8 billion 99 crores

Kathmandu. On the first trading day of the week, the NEPSE index decreased by 22.33 points and remained at the point of 2791.71. During the day, 21.842 thousand 887 shares of 329 companies were bought and sold, totaling 8.999 billion 2.6 million s...

After the highway was blocked, gas for Kathmandu valley started to be filled from outside

Chitwan. After the road was washed away in Krishnabhir on the Prithvi Highway, cooking gas has been filled and sent to the valley in the industries outside the federal capital Kathmandu. Since the gas-laden bullets could not enter Kathmandu due to...

Stock market of the week: NEPSE increased on all five days of trading

Kathmandu. In the stock market this week, the NEPSE index, which measures stock trading, has risen for five consecutive days. From Sunday to Thursday, the overall market index increased by more than four decimal points...

The price of gold decreased, how much per tola on Friday?

Kathmandu. Even today, the price of gold in the Nepali market is falling. Gold has decreased by Rs 900 per tola. According to the Nepal Gold and Silver Traders Federation, gold is being traded at 252,400 rupees per tola today. On the other hand, s...

Tulsi Ram Agarwal, Chairman of Nishi Asia Bank, has resigned

Kathmandu. Tulsi Ram Aggarwal, Chairman of NISH Asia Bank, has resigned. Agarwal submitted his resignation letter in the meeting of the board of directors held on Sunday. The bank informed that his resignation was accepted at the same meeting. The...

Federation's objection to industrialists' strike and preparation for power cut

Kathmandu. Federation of Nepal Chamber of Commerce and Industry (FNCCI) has expressed serious concern about the preparations to cut the power lines of the industries within the industrial area run by the Industrial Zone Management Limited and crea...