This is how the work of the new road is going on in Krishnabhir, preparing to open it in August

Main News Image

Kathmandu. The Prithvi Highway has been blocked for 14 days after the flood that came to Trishuli via Bhotekoshi eroded the lower part of the road along the river bank. On August 14, 100 meters of the road was washed away after Trishuli cut the base of the road at Krishnabhir in Dhading, which is considered to be the main lifeline connecting Kathmandu.  

The work of opening a new track above the Krishnabhir river and preparing it for the smooth movement of vehicles is going on in full swing. The work of cutting the hill and connecting the 250 meter track on both sides has been completed.

Sajna Adhikari, head of planning for the Nagadhunga-Mugling road project, said that the gravel and rolling work will start from Sunday and will be completed within 3-4 days by the end of August. "Graveling is not as easy as cutting. It should be mixed by rolling. It should be done in layers. It cannot be done in one layer," she said, "that's why it may take 3-4 days. The goal is to operate the transport from the end of this month.

mediabaaji add

Related News

Earthquake centered around Rayal in Bajhang

Kathmandu. The epicenter of the earthquake was around Rayal in Bajhang district. According to the National Earthquake Measurement and Research Center Lanchaur, an earthquake of magnitude 4.1 took place today at 1:14 PM with its epicenter near Raya...

Chance of very heavy rain in these four provinces today, request to be cautious

Kathmandu. According to the weather forecast division, the influence of monsoon air is currently affecting the country. At present, the Monsoon low pressure line is slightly above Sardar place in the west around the Terai region of Nepal and aroun...

Establishment of Response Base for Monsoon Disaster Mitigation

Baitadi As the time of active monsoon is approaching, the Armed Police Force of Nepal has established a temporary monsoon response base in Baitadi to minimize the damage that may be caused by natural disasters.

A temporary monsoon response b...

New driver's license fully safe, practical and quality: Ministry of Communication

Kathmandu. The Ministry of Communication and Information Technology announced the latest progress regarding the printing of smart driver's license, technology and security enhancement and said that the currently implemented system is more secure a...

Government's decision to give public holidays on Saturdays and Sundays, offices will open from nine o'clock

Kathmandu. The Cabinet meeting held on Sunday decided to make Saturday and Sunday public holidays. Government spokesperson Sasmit Pokharel informed that the meeting of the Council of Ministers held today has decided to give a holiday to government...

Electricity supply will be affected in various areas of Kathmandu from today till 14th

Kathmandu. The Nepal Electricity Authority has said that the power supply will be affected in various areas of Kathmandu as they have to remove old relays and install and test new relays at Teku substation. The Lapsiphedi and Changunarayan substat...