This is how the work of the new road is going on in Krishnabhir, preparing to open it in August

Main News Image

Kathmandu. The Prithvi Highway has been blocked for 14 days after the flood that came to Trishuli via Bhotekoshi eroded the lower part of the road along the river bank. On August 14, 100 meters of the road was washed away after Trishuli cut the base of the road at Krishnabhir in Dhading, which is considered to be the main lifeline connecting Kathmandu.  

The work of opening a new track above the Krishnabhir river and preparing it for the smooth movement of vehicles is going on in full swing. The work of cutting the hill and connecting the 250 meter track on both sides has been completed.

Sajna Adhikari, head of planning for the Nagadhunga-Mugling road project, said that the gravel and rolling work will start from Sunday and will be completed within 3-4 days by the end of August. "Graveling is not as easy as cutting. It should be mixed by rolling. It should be done in layers. It cannot be done in one layer," she said, "that's why it may take 3-4 days. The goal is to operate the transport from the end of this month.

mediabaaji add

Related News

Landslide in Baglung: 10 people died in two days, 24 houses were damaged in Tanahun

Baglung. 10 people died and one person went missing in Baglung due to the landslides that followed the incessant rain. In the last two days, landslides have caused huge human losses in the district. On Sunday alone, 9 people have died and one pers...

Chance of snowfall in high hills and mountain areas

Kathmandu. At present, there is a partial effect of western low pressure system in Nepal. At present, there is haze in some places of the Terai region.

According to the Weather Forecast Division, there are partly cloudy areas in the hilly an...

Rain will occur in some parts of the country on Monday

Kathmandu. On Monday, it will be generally cloudy over hilly and mountainous areas of Koshi, Madhesh, Bagmati, Gandaki and Lumbini regions and Karnali and Sudurpaschim regions. It will be partly cloudy in the rest of the area. According to the wea...

Aiming to open the road from October 1st, 20 buses with gas bullets left Krishnabhir

Kathmandu. On Sunday, 21 large vehicles left Kathmandu after the road blocked by landslides in Krishnabhir due to floods in Bhotekosi and Trishuli was reopened. The road department issued a press release in the evening and said that 'about 20 ligh...

Heavy rain will occur in Koshi, Bagmati and Gandaki regions today

Kathmandu. At present, the influence of Monsoon air is present in the whole country. At present, the low pressure line of Monsoon is near the Terai area of ​​Nepal a little above Sardar place.

 As a result, there is a possibility of ver...

The number of people going out of Kathmandu to vote in the election has increased, vehicles will be running until the 20th

Kathmandu. The number of citizens returning to their home districts from the capital Kathmandu has started to increase rapidly, targeting the House of Representatives elections to be held on February 21. Voters who are engaged in various professio...