Muglin -Malekhu road upgradation work started
Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.
According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.
According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.
This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.
Express
Related News
Government's decision to give 50% customs tax exemption on import of petroleum products
Kathmandu. The government has decided to provide a 50 percent discount on customs duty and infrastructure development tax on the importation of petrol, diesel and kerosene. Federal Affairs and General Administration Minister Pratibha Rawal has inf...
This week, NEPSE has decreased by normal numbers, how much is the transaction on which day?
Kathmandu. This week, NEPSE index decreased by 0.56 points and reached 2714.05 points. NEPSE, which closed at 2714.61 points last week, decreased by 73.18 points to 2714.05 points this week. The market was open for five trading days this week. In...
Construction of two hydropower projects of 84 megawatt capacity in Rahughat of Myagdi has been completed
Kathmandu. Tundi Power Company has simultaneously constructed two hydropower projects on the Rahughat River that flows through Raghuganga Rural Municipality of Myagdi. Ghuganga Rural Municipality-4, 7 and 8 Ward No. 4, 7 and 8 of the two projects...
Question to the Minister of Finance: What source of income did you see and are you going to increase the salary of the employees?
Rusha Thapa
Kathmandu. More than five years have passed since cooperatives, microfinance, and finance collapsed. Now the crisis has started to appear in the bank as well. It has been the same time that the country has been in economic recess...
Revenue collection of 21 lakh 10 thousand in one day in traffic action
Kathmandu. In the past 24 hours, two thousand 102 motorists have been prosecuted for violating traffic rules. From this, the revenue of Rs 21 lakh 10 thousand 514 has been deposited in the state treasury. According to the Kathmandu Valley Traffic...
The 12-year blockage of Dhalkebar-Hetaunda 400 KV transmission line has been removed
Kathmandu F. The government has removed the main obstacle to the construction of Dhalkebar Hetaunda 400 KV high voltage transmission line, which has been stalled for various technical and legal reasons for the past 12 years. With the important dec...