Muglin -Malekhu road upgradation work started
Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.
According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.
According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.
This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.
Express
Related News
Completed the financial management of Jaldigarh hydropower project, collected 4 billion 60 crores
Kathmandu. The financial management of the 22.50 MW Jaldigarh hydropower project to be built in Athabiscot Municipality of Rukum West has been completed. Investment worth 4.6 billion rupees has been collected for the project promoted by Shangrila...
Foreign currency exchange rate set for today
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to Rashtra Bank, the buying rate of one US dollar has been fixed at 153 rupees 28 paisa and the selling rate is 153 rupees 88 paisa.
The b...
LPG filling outside the valley after the road to Krishnaveer was washed away
Chitwan. Gas wettings are being filled outside the capital after the road was washed away in the Krishna Ghati of Prithvi Highway. After the bullets carrying gas could not go, the gas industry of the valley and neighboring districts are going to t...
The Euro and Pound fell modestly today as the US Dollar held steady
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the fixed exchange rate, while the US dollar remained stable, the value of European Euro, UK Pound Sterling decr...
Shangrila Development Bank declares 10 percent dividend
Kathmandu. The meeting of the board of directors of Sangrila Development Bank Limited held on the afternoon of 28th October has announced the dividend to the shareholders.
The meeting has announced that 5% bonus s...
Electricity of Bheri-Babai project will be connected to national transmission: 132 kV transmission line is being constructed
Surkhet. The process of connecting the electricity produced by the national pride Bheri-Babai diversion multi-purpose project to the national transmission system has started.
In order to connect the electricity produced by the project to the...