Muglin -Malekhu road upgradation work started

Main News Image

Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.

According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.

According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.

This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.

mediabaaji add

Related News

What is the exchange rate of which foreign currency on Monday?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the fixed rate, the buying rate of one US dollar is 144 rupees 02 paisa and the selling rate is 144 rupees 62 paisa. 

Similarly, t...

Monitoring of 56 commercial firms in one day

Kathmandu. The Department of Commerce, Supply and Consumer Protection has monitored 56 commercial firms on the same day at various locations in Kathmandu on Wednesday. The department has conducted on-site monitoring of firms, shops and commercial...

The price of the American dollar is the highest so far, how much is one dollar Nepalese rupee?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for Saturday today. According to the fixed exchange rate, the value of the US dollar has reached its highest point so far. The buying r...

The government's decision to give tax exemptions to China

Kathmandu. The government has decided to provide tax exemptions for the purchase and export of necessary materials for the expansion of the second section of the ring road. With this decision, the way has been opened to proceed with the process of...

In one day, gold rose by 7,000 tolas and set a new record, how many tolas will be traded today?

Kathmandu. The price of gold in the Nepalese market has reached a historic high. Gold has increased by 7 thousand 100 rupees in a single day and has reached its highest price so far.
According to the Nepal Gold an...

Re-operation after five months at Satighat of Arun river

Bhojpur. The Arun river ferry service at Satighat, which connects Bhojpur and Sankhuwasabha from the north, has resumed operation after six months. The ferry, which has been closed since last May due to rain, has been brought back into operation f...