Muglin -Malekhu road upgradation work started
Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.
According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.
According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.
This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.
Express
Related News
Kalanga Hydro's IPO collects 2 billion rupees, how many applied?
Kathmandu. 2 billion 25 lakh 29 thousand rupees have been collected in the IPO of Kalanga Hydro Limited. According to CDS, 17 lakh 79 thousand 593 people have applied for 2 crore 25 thousand 290 shares till 5 pm today on 10th May. The company has...
Fixed foreign currency exchange rates
Kathmandu. The foreign currency exchange rate determined by Nepal Rastra Bank today is stable. According to the National Bank, today the same rate as yesterday is maintained. Today, the buying rate of one US dollar is 151 rupees 61 paisa and the s...
Ministry's directive to refund fees collected illegally from students
Kathmandu. The Ministry of Education, Science and Technology has directed all concerned to refund the illegally collected fees to the students. The ministry issued a statement on Wednesday and directed some institutional schools to return the amou...
More than 2.7 million smart licenses were sent to the offices for distribution
Kathmandu. The Transport Management Department has completed the printing of driver's license (Smart License) which has been stopped for the past four years and has accelerated the distribution process.
The department issued a statement and...
National Life earned a profit of 148 million rupees in the first quarter, insurance fund close to 1 billion
Kathmandu. National Life Insurance Company Limited has earned a net profit of Rs 148 million in the first quarter of the current financial year. The company's net profit has increased by 1.81 percent compared to Rs. 13...
The stock market increased by 33.27 points, turnover above 10 billion
Kathmandu. A significant improvement was seen in the stock market on Wednesday. Today NEPSE index increased by 33.27 points to 2866.87 points, which is an increase of 1.17. In today's trading, when 2 crore 64 lakh 38 thousand shares were bought an...