Muglin -Malekhu road upgradation work started
Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.
According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.
According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.
This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.
Express
Related News
As the students started to get sick due to the rising heat, the school hours were changed and classes were held on Sundays as well
Kathmandu. With extreme heat in Kanchanpur, the two local levels here have changed the timing of school operations. Keeping in mind the adverse effects of heat on the health of students, Krishnapur and Shuklaphanta Municipalities have decided to o...
The Nagdhunga-Sisnekhola Tunnel will be commercially operated from Saun
Kathmandu. The Nagdhunga-Sisnekhola Tunnel, Nepal’s first modern transport tunnel, is being prepared for full commercial operation from the second week of next Saun. Providing information on the project’s current progress and operational plan, Pro...
4 points of agreement between the agitating sugarcane farmers and industrialists in Sarlahi, to be paid within a month
Surlahi. A four-point agreement has been reached between the farmers and the industrial side, who are on a dharna demanding the arrears of sugarcane sold to the Annapurna sugar industry in Dhankaul, Sarlahi. On the ini...
Iran turning problems into opportunities, making billions of dollars under the guise of war
Kathmandu. Iran has turned the war with the US and Israel into an opportunity. The U.S. targeted military bases near the island of Kharg Iran, but did not directly target an oil terminal for fear of a global oil crisis. Taking advantage of this, I...
The price of the US dollar, Australian dollar, euro and pound increased!
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currencies for Saturday. Today, the value of all foreign currencies including US Dollar, Australian Dollar, Euro, Pound, Kuwaiti and Bahraini Dinar has increased. According t...
Collected more than 11 billion in Prime Minister's Disaster Fund
Kathmandu. Relief and financial support for the flood victims of Rasuwa is increasing. According to the Office of the Prime Minister and Council of Ministers, there is currently 11.55 billion 56 lakh 26 thousand 971 in the Prime Minister's Disaste...