'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
The price of gold and silver increased, now how much per tola?
Kathmandu. Today on March 3, the price of gold and silver has increased in the Nepalese market. Gold has increased by Rs 400 per tola while silver has increased by Rs 70 per tola.
The Nepal Gold and Silver Traders Federation has informed tha...
Extension of Pokhara-Muglin road affected due to non-removal of electricity poles
Kathmandu. The construction of the Pokhara section under the Pokhara-Muglin road project has been affected due to the non-removal of the poles of the 11 kV dedicated power line taken to the Pokhara International Airport. Due to the non-removal of...
The Election Commission received 6 billion 73 million rupees
Kathmandu. The Ministry of Finance has revised and increased the approved budget for the House of Representatives elections. The Commission had requested a budget of 7.81 billion rupees for the election, but the Ministry of Finance cut it by 40 pe...
The farmers did not get the right price for the ripe oranges in the orchards of Baglung
Baglung. Orange orchards in the rural areas of Baglung have turned yellow at this time. However, the farmers have complained that they are not getting a fair price even though the orchards are looking good after the oranges have ripened. They said...
Today's foreign currency exchange rate: what is the price of dollars, euros and pounds?
Kathmandu. According to the exchange rate of foreign currency determined by Nepal Rastra Bank for today, the buying rate of one US dollar has remained at 152 rupees 04 paisa and the selling rate has remained at 152 rupees 64 paisa.
Similarly...
The stock market increased by 10 points, turnover of 4 billion 45 million
Kathmandu. On Wednesday, the stock market increased by 10.30 points. With the increase of that number, the market index NEPSE has remained at 2648.90 points. The previous day, NEPSE increased by 21 points. The transaction amount has generally incr...