'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
Bringing casinos into more legal ambit, the department issued a 12-point directive
Kathmandu. The government has issued various 12-point directives with the aim of bringing the casino, which is a commercial entertainment sector, under more legal scope. The Department of Tourism under the Ministry of...
The Gas Industry Association will provide a thousand 250 cylinders free of charge to the flood-affected
The Kathmandu. The Nepal LP Gas Industry Association has provided 1,250 gas cylinders to the people affected by the devastating flood in the Bhotekoshi River in Rasuwa. The association has announced to provide gas as a humanitarian aid to the...
After the interest of the Prime Minister, the closed tea industries are re-opening
Kathmandu. The tea industries of Jhapa and Eelam, which were closed for the past few days, have resumed operations due to India's restrictions on tea exports. After the government promised to form a special task force to solve the problems of the...
Gold has fallen from its highest price, while silver has hit a new record
Kathmandu. The price of gold has decreased from its highest value so far. Gold today fell by Rs 600 per tola. According to the Nepal Gold and Silver Traders Federation, today the price of gold is being bought and sold at 270,000 rupees per tola. O...
The price of gold increased, how much per tola on Thursday?
Kathmandu. The price of gold has increased in Nepali market today. Gold tola has gone up by 800 rupees. According to the Nepal Gold and Silver Traders Federation, gold is being traded at 284,000 rupees per tola today. The price of 10 grams of gold...
Today is the exchange rate of foreign currency, how much of which country?
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the National Bank, the value of the US dollar has increased. The buying rate of one American dollar is fixed at 140 rupees 47 paisa and the s...