'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months

Main News Image

Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.

"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."

Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.

mediabaaji add

Related News

This week, NEPSE increased by normal numbers, which day's business is how much?

Kathmandu. This week, the NEPSE index increased by 0.89 points and reached 2641.43 points. NEPSE, which closed at 2640.54 points last week, increased by 0.89 points to 2641.43 points this week. The market was open for only three trading days this...

Twenty-four thousand five hundred megawatts of electricity will be produced in the next ten years

Kathmandu. The government has published the 'Energy Consumption Growth and Export Strategy, 2083' with the goal of producing a total of 24,500 megawatts of electricity by the end of the fiscal year 2092, 93 with investment from the government, pub...

The value of the dollar did not change today, so did the exchange rate of other foreign currencies

Kathmandu. Nepal Rastra Bank has determined the foreign currency exchange rate for today. According to Rashtra Bank, the buying rate of one US dollar has been fixed at 152 rupees 59 paisa and the selling rate is 153 rupees 19 paisa.

The valu...

Fuel supply from Tribhuvan Rajpath after the road was washed away in Krishnabhir

Kathmandu. After the road was blocked in the Krishnabhir section of Dhading under the Prithvi Highway, Nepal Oil Corporation is continuing to supply petroleum products and LP gas to Kathmandu Valley and surrounding areas through the alternative ro...

Completed the financial management of Jaldigarh hydropower project, collected 4 billion 60 crores

Kathmandu. The financial management of the 22.50 MW Jaldigarh hydropower project to be built in Athabiscot Municipality of Rukum West has been completed. Investment worth 4.6 billion rupees has been collected for the project promoted by Shangrila...

Construction permission for 10 hydropower projects till mid-October

Kathmandu. The Electricity Development Department has granted construction permits to a total of 10 hydropower projects in the first quarter of the current year. The total capacity of that project is equal to 241.50 megawatts. The department has g...