'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
Construction of Kohalpur-Surkhet 132 KV transmission line has been completed
Kathmandu. Nepal Electricity Authority has completed the construction of Kohalpur-Surkhet 132 KV transmission line. The construction of the Kohalpur-Surkhet section has been completed under the Kohalpur-Surkhet-Dailekh 132 KV transmission line pro...
Imports of LP gas fell by 40.8 percent in a single day, only 128,332 cylinders were imported on August 26.
Kathmandu. There has been a significant decline in the daily import of LP gas in Nepal. According to the data of the Customs Department under the Ministry of Finance, the total import of LP gas on August 26 has decreased by 40.8 percent compared t...
The value of the US dollar increased!
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the exchange rate set for today, the value of the US dollar has increased again. According to the determined exchange rate, the buying rate o...
Opening of Nagadhunga tunnel tomorrow, only emergency vehicles will be allowed to ply
Kathmandu. Nepal's first modern transport tunnel 'Nagadhunga-Sisnekhola Tunnel' will be formally inaugurated from Monday.
The total cost of this project, which was completed with the concessional loan of Japan International Cooperation Agenc...
Shikhar Power's IPO allotment, 24 lakh 66 thousand applicants empty handed
Kathmandu. Shikhar Power Development Limited opened the sale to the general public from February 17th to 26th, and the IPO was distributed today on March 3rd by Global IME Capital Limited, the sales manager. The company got permission from the Nep...
Rajan Vikram Thapa appointed as the Chairman of Nepal Insurance Authority
Kathmandu. The government has appointed Rajan Vikram Thapa as the chairman of Nepal Insurance Authority. Based on the recommendation of the selection committee formed by the Ministry of Finance, the Cabinet meeting held on Tuesday appointed Thapa...