'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months

Main News Image

Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.

"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."

Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.

mediabaaji add

Related News

What is the exchange rate of which foreign currency on Tuesday?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the determined exchange rate, the buying rate of one American dollar is 145 rupees 16 paisa and the selling rate is 145 rupees 76 paisa. The...

More liquidity in the banking system, with the National Bank drawing a trillion rupees from the market

Kathmandu. Nepal Rastra Bank is going to issue a 91-day deposit collection tool worth one trillion rupees on Wednesday to manage the continuously increasing excess liquidity in the banking system. Since the last few months, there is more than enou...

Development expenditure only 23.58 percent in nine months

Kathmandu. In the nine months of the current fiscal year 2082/83, the government has spent about 54 percent of the budget. The government had brought a budget of 19 trillion 64 billion rupees for the current financial year. Out of that, the govern...

A huge increase in the price of gold, how much is the transaction?

Kathmandu. On the first trading day of the week, the price of gold rose in the Nepali market on Sunday. Today, gold has increased by 9 thousand 500 rupees. Gold which was traded at 2 lakh 91 thousand rupees on Friday is being traded at 3 lakh 500...

Adding date of commercial production of hydropower projects

Kathmandu. The Nepal Electricity Authority has prepared to add RCOD to the final date for starting commercial production of hydropower projects that have not been able to start commercial production due to various reasons despite the PPA.

Th...

Heavy fall in the price of gold and silver, how much is the transaction going on today?

Kathmandu. The price of gold has decreased in the Nepalese market. Today the price of gold has decreased by 9 thousand 500 rupees per tola. According to the Nepal Gold and Silver Traders Federation, 2 lakh 95 thousand 200 rupees have been fixed in...