'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
Completed the financial management of Jaldigarh hydropower project, collected 4 billion 60 crores
Kathmandu. The financial management of the 22.50 MW Jaldigarh hydropower project to be built in Athabiscot Municipality of Rukum West has been completed. Investment worth 4.6 billion rupees has been collected for the project promoted by Shangrila...
The Australian dollar, euro and pound fell, while the Bahraini dinar rose
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currencies for Monday. Even today, the US dollar remains at a high value. Some currencies, including the Bahraini dinar, have appreciated. According to Nepal Rastra Bank, the...
Salt Trading Corporation to distribute 10 percent dividend
Kathmandu. Salt Trading Corporation is going to distribute 10 percent dividend. The company has announced that it will distribute the dividend to its shareholders from the profit of the last financial year. In which the company is going to distrib...
The Nagdhunga-Sisnekhola Tunnel will be commercially operated from Saun
Kathmandu. The Nagdhunga-Sisnekhola Tunnel, Nepal’s first modern transport tunnel, is being prepared for full commercial operation from the second week of next Saun. Providing information on the project’s current progress and operational plan, Pro...
Sabhakhola 'B' hydropower project tunnel 'break through'
Kathmandu. The tunnel of the under-construction Sabhakhola 'B' hydropower project in Sabhapokhari Rural Municipality of Sankhuwasabha has been breached. The main tunnel of the 21.5 MW Sabha Khola project, which is under construction using Sabha Kh...
How was the weather across the country on Friday?
Kathmandu. Currently, there is no significant impact of any weather system across the country, according to the Water and Weather Forecast Division.
According to the division, the weather will remain mostly clear...