'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
NEPSE decreased by 10 points, turnover exceeded 5 billion!
Kathmandu. On Sunday, the first day of the week, the NEPSE index fell by 10.29 points to 2,610.63. About 1.3 million shares of 323 companies were traded, with a total turnover of 5.01 billion rupees. Out of the 13 sub-groups, hotels, manufacturing...
Today, NEPSE increased by 30.75 points, turnover above 9 billion 20 million
Kathmandu. On the first trading day of the week, the stock market NEPSE index increased by 30.75 points and reached the point of 2631.14. On NEPSE, 297 million 38 thousand 139 shares of 300 companies were bought and so...
The tenth amendment of the National Bank Act 2058
Kathmandu. The Ministry of Finance has started the process of amending the existing legal structure related to Nepal Rastra Bank. The ministry has released the draft of the bill to amend the Nepal Rastra Bank Act, 2058 and has sought opinions and...
NEPSE decreased by 10.53 points today, turnover of 4 billion 77 crores
Kathmandu. On the second trading day of the week, the NEPSE index decreased by 10.53 points and remained at the point of 2622.88. During the day, 1337 thousand 307 shares of 337 companies were bought and sold, and 4 billion 774 million shares were...
Solu Hydropower's IPO will be distributed next week
Kathmandu. The IPO of Solu Hydropower Limited will be distributed only next week. Nabil Investment Banking Limited and Himalayan Capital Limited as sales managers have informed that they are working to distribute the IPO only.
In the company...
Shortage in the market as LP gas supply from India is inconvenient
Kathmandu. For the last one week, since LP gas could not be imported from India as per the demand, the supply in the Nepali market has become difficult. As a result, consumers have to face shortages. According to the Nepal Oil Corporation, since t...