'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
Suggestion of transport operators to levy additional charges on fuel and electric charging units
Kathmandu. The umbrella organization of transporters, the National Association of Transporters, Nepal has suggested an additional fee of Rs.
Submitting separate memorandums to Infrastructure Development Minister Sunil Lamsal and Law, Justice...
Vehicles are running on Nagadhunga tunnel from today: Nepal is entering the tunnel age
Kathmandu. The dream of the Nepalese people for years to run vehicles in the tunnel has finally been realized. The much-awaited Nagadhunga tunnel, which was built on November 14, 2019, has been formally opened for traffic from Monday.
The sp...
ADB Project’s Rs 420 Million Budget Under Scrutiny, Consultant Selection Sparks Controversy
Kathmandu — The consultant and service provider selection process under the Rural Connectivity Improvement Project, implemented through the Department of Local Infrastructure Development with support from the Asian Development Bank, has come under...
Foreign Currency Exchange Rate: What is the price of US Dollar and Euro?
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the Central Bank, today the buying rate of one US dollar has been fixed at 152 rupees 06 paisa and the selling rate has been fixed at 152 rup...
What is the exchange rate of which country on Tuesday?
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the determined exchange rate, the buying rate of one US dollar is 144 rupees 75 paisa and the selling rate is 145 rupees 35 paisa.
Simi...
Contracts of 25 construction companies that did not work according to the contract were terminated
Kathmandu. The government has terminated the contract with 25 construction companies that did not complete the construction as per the contract. Federal Road Supervision and Monitoring Office Kathmandu under the Road D...