Adding date of commercial production of hydropower projects
Kathmandu. The Nepal Electricity Authority has prepared to add RCOD to the final date for starting commercial production of hydropower projects that have not been able to start commercial production due to various reasons despite the PPA.
The Authority has put forward a new RCOD management policy by classifying the hydropower projects into four different groups based on the on-site condition of the construction, the condition of fulfilling the obligations mentioned in the PPA and the overall physical progress.
The meeting of the Board of Directors of the Authority held on 32nd June has taken a formal decision to classify the projects that have PPA but have not yet been put into commercial operation into 'A', 'B', 'C' and 'D' groups.
Express
Related News
Bamjan Acquitted in Money Laundering Case
Kathmandu: The Sarlahi District Court has acquitted Ram Bahadur Bamjan, known as the Little Buddha, in a money laundering case. On Baisakh 8, a bench led by Judge Mahendra Raj Kafle ruled that the charges in the case were not substantiated and dec...
Foreign currency exchange rate: What is the value of dollars, euros and pounds?
Kathmandu. Nepal Rastra Bank has determined the official exchange rate of foreign currency for today. According to the central bank, the buying rate of one US dollar has been fixed at 152 rupees 40 paise and the selling rate has been fixed at 153...
A money-laundering case in Galle
Dhading. A locker containing money has been found in a mud-filled condition on the Prithvi Highway in Galchhi Village-6 Bareni of Dhading. A nine-member team from Armed Police Force Nepal Disaster Management Base Adamghat, led by Armed Police Depu...
The price of gold increased suddenly, how much per tola will be traded on Friday?
Kathmandu. The price of gold has increased in Nepali market today. Gold tola has increased by 2 thousand 100 rupees. According to the Nepal Gold and Silver Traders Federation, today, gold has been fixed at 267,800 rupees per tola.
On the oth...
Testing of Kohalpur-Surkhet 132 KV Power Transmission Line
Surkhet. The much awaited Kohalpur Surkhet 132 KV power transmission line has been tested. After the construction of the project was completed, the line was tested on Friday. With the completion of the construction of 132 KV transmission line, it...
Double-digit decline in the stock market, turnover also decreased
Kathmandu. There was a double-digit decline in the stock market on Thursday. On this day, the NEPSE index decreased by 19.67 points and stood at 2601.92 points. As the NEPSE index fell, the turnover also decreased compared to Wednesday. On the pre...