'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
NEPSE increased by 12.78 points throughout the week, how much is the transaction on which day?
Kathmandu. This week, the NEPSE index increased by 12.78 points and reached 2654.93 points. NEPSE, which closed at 2642.15 points last week, increased by 12.78 points to 22654.93 points this week. The market was open on all five trading days this...
The World Bank will give 50 million dollars for Nepal's digital transformation
Kathmandu. The World Bank is going to give 50 million dollars for Nepal's digital transformation. Recently, the Executive Board of Directors of the World Bank, sitting in Washington, has decided to give this support to Nepal under the 'Nepal Digit...
Heavy damage to power sector due to Bhotekoshi flood, 12 projects of 431 MW closed
Kathmandu. About 10 percent of the country's total power generation capacity has been affected due to the floods in the Bhotekoshi River in Rasuwa. After the floods caused great damage to power generation, transmission and distribution structures,...
What is the exchange rate of which foreign currency on Tuesday?
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the exchange rate set for today, the value of the US dollar has increased. According to the fixed exchange rate, the buying rate of one US do...
Monitoring of 56 commercial firms in one day
Kathmandu. The Department of Commerce, Supply and Consumer Protection has monitored 56 commercial firms on the same day at various locations in Kathmandu on Wednesday. The department has conducted on-site monitoring of firms, shops and commercial...
The price of gold and silver decreased, how much of the tola?
Kathmandu. On the third trading day of the week, the price of gold fell on Tuesday. Compared to the previous trading day, the price of gold has decreased by Rs 4500 per tola. On the previous day of trading, the price of gold, which was traded at 2...