Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
Hotel View Bhrikuti has announced a special offer for the English New Year
Lalitpur. Hotel View Bhrikuti has announced a special festive offer for guests on the occasion of Christmas and English New Year 2026. The hotel management said that the offer will be applicable from December 24, 2025 to January 1, 2026.
What is the foreign currency exchange rate on Monday?
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the Rashtra Bank, the buying rate of one US dollar has been fixed at 141 rupees 70 paisa and the selling rate ha...
The construction company's commitment to complete Kamala Bridge within three months
sirah After the physical infrastructure and transport minister Kulman Ghisingh's on-site inspection and instructions, the construction company has committed to complete the unfinished Kamala bridge connecting Dhanusha...
Emphasis on Nepal-China economic cooperation
Kathmandu. Finance Minister Rameshwar Khanal emphasized on Nepal-China economic cooperation and investment growth. In a workshop on Nepal-China economic cooperation and investment held here on Tuesday, Minister Khanal...
Advice to candidates by the Election Commission: Do not delay in opening a bank account
Kathmandu. The Election Commission has advised the House of Representatives candidates not to delay in opening bank accounts. In a press conference held on Friday, the commission informed all the candidates that they have to spend from this accoun...
Mandatory IT audit system implemented in Nepal Stock Exchange for brokers
Kathmandu. Nepal Stock Exchange NEPSE has issued 'IT Audit Guidelines-2026' to make the digital infrastructure of the capital market safe and reliable and has implemented a mandatory information technology IT audit system for broker companies.
...