'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
China to launch new action plan to strengthen digital currency management and operations
Kathmandu. China has announced that it will launch a new 'action plan' to strengthen the management and operation of its digital currency from January 1. Lu Lei, the deputy governor of People's Bank of China PBOC, the country's central bank, gave...
1900 cooperatives in Kathmandu metropolis, half of them do not submit reports
Kathmandu. About 1,900 cooperatives are operating within the Kathmandu Metropolitan City. Even 50 percent of the operating cooperatives do not submit reports regularly. The fact that there are more cooperatives that do not report regularly means t...
MDRT honor and training program of National Life completed
Kathmandu. National Life Insurance Company Ltd. has completed the MDRT honor and training program under the chairmanship of Chief Hospitality and Chief Executive Officer Mrs. Prema Rajya Lakshmi Singh, President of the company at Dushit Thani Hima...
Here are the foreign currency exchange rates set for Friday
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for Friday. According to the determined exchange rate, the buying rate of one US dollar is 147 rupees 92 paisa and the selling rate is 148 rupees 52 paisa. Similarly...
Discussion of Deuba in UML meeting, criticism of Oli
Kathmandu. CPN-UML Central Committee meeting continues from Tuesday. The central members are giving their views in the meeting. Party President KP Sharma Oli presented a political proposal on Tuesday.
Other leaders of the...
The price of gold increased on Tuesday, now how much per tola?
Kathmandu. The price of gold has increased in Nepali market today. Gold tola has gone up by 1 thousand 600 rupees. According to the Nepal Gold and Silver Traders Federation, today gold is being bought and sold at 3 lakh 1 thousand 300 rupees per t...