'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months

Main News Image

Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.

"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."

Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.

mediabaaji add

Related News

Salary of Child Development Facilitator, School Staff and School Helper increased by 5,000

Kathmandu. On the proposal of the Ministry of Education and Sports, the government has decided to increase the salary subsidy of teachers and early childhood development ECD facilitators and school staff working on federal grants. The Cabinet meet...

NEPSE closed with a double-digit decline today, trading fell to 4.71 billion

Kathmandu. On the fifth trading day of the week, NEPSE index decreased by 12.83 points and remained at the point of 2620.92. Today, 1 crore 1 lakh 53 thousand 226 shares of 342 companies were bought and sold, and 4 billion 71 crore 39 lakh shares...

LPG filling outside the valley after the road to Krishnaveer was washed away

Chitwan. Gas wettings are being filled outside the capital after the road was washed away in the Krishna Ghati of Prithvi Highway. After the bullets carrying gas could not go, the gas industry of the valley and neighboring districts are going to t...

Twenty-four thousand five hundred megawatts of electricity will be produced in the next ten years

Kathmandu. The government has published the 'Energy Consumption Growth and Export Strategy, 2083' with the goal of producing a total of 24,500 megawatts of electricity by the end of the fiscal year 2092, 93 with investment from the government, pub...

Juice production after kiwis are not sold

Baglung. The women of Tarakhola rural municipality have started producing kiwi juice. Five years ago, women planted kiwis all over the fields in the village hoping to sell them at a high price, but now they are unable to find a market, so they hav...

Rastra Bank is issuing 20 billion rupees bonds today

Kathmandu. Nepal Rastra Bank is going to issue bonds worth 20 billion rupees again today on January 23rd. The Central Bank is going to issue 'Nepal Rastra Bank Bond 2083 E' today. This bond will be discussed online till 2 pm today. The interest ra...