'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
Hams Hospital to launch IPO
Kathmandu. Hospital for Advanced Medicine and Surgery Limited Hams Hospital has called the annual general meeting with the proposal of IPO issue. The meeting of the board of directors of the hospital held on 5th July decided to hold the Annual Gen...
The price of the US dollar at the highest point so far! Now how much Nepali rupee is one dollar?
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the National Bank, the value of the US dollar has reached its highest point so far. Similarly, the prices of for...
Extension of application deadline for companies dealing in real estate
Kathmandu. The Department of Land Management and Records has extended the deadline for applications for firms, companies or organizations that want to get a license to deal with real estate. The department has extended...
Rashtra Bank's request to provide banking services even during Tihar holidays
Kathmandu. Nepal Rastra Bank has requested banks and financial institutions to conduct banking services for customs clearance on days other than Bhaitika. The central bank has written to the banks and financial institu...
Demand for subsidized salt in Solukhumbu increasing, sales of over 7.2 million in a year
Solukhumbu. In Solukhumbu, the consumption of iodized salt which is being distributed at subsidized rates has increased. The salt that is being provided by Salt Trading Corporation Limited at Rs 9 per packet has been sold for more than Rs 72 lakh...
Foreign currency exchange rate: What is the value of the Kuwaiti dinar and the pound with the US dollar?
Kathmandu. Nepal Rastra Bank has determined the official exchange rate of foreign currency for today. According to the new rate issued by the Central Bank, today the buying rate of one US dollar is 153 rupees 68 paisa and the selling rate is...