November 13, 2026, Friday
English

'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months

Main News Image

Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.

"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."

Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.

mediabaaji add

Related News

The value of the US dollar at a high point!

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for Sunday. According to the fixed exchange rate, the value of the US dollar has reached a high point. According to the determined exchange rate, the buying rate of...

The price of gold and silver increased, now how much per tola?

Kathmandu. Today on March 3, the price of gold and silver has increased in the Nepalese market. Gold has increased by Rs 400 per tola while silver has increased by Rs 70 per tola.

The Nepal Gold and Silver Traders Federation has informed tha...

Sharp Decline in Gold Prices: Down by 3,800 in a Single Day, Silver Also Becomes Cheaper

Kathmandu — The prices of both gold and silver fell sharply in the Nepali market today. According to the Nepal Gold and Silver Dealers’ Federation, the price of gold dropped by Rs 3,800 per tola today. With this decline, the price of hallmark gold...

With the new financial year, the burden of taxes was added: From today, these seven sectors will become more expensive for consumers

Kathmandu. The government is going to implement new taxes and additional charges on various goods and services from the beginning of the new financial year i.e. from 1st July. With the aim of strengthening internal revenue collection and raising f...

32 points decline in NEPSE, turnover of 21.5 billion

Kathmandu. The NEPSE index fell on the third trading day of the week on Tuesday. The stock market, which closed with a historic increase of 162 points the previous day, corrected by 32.08 points today. Along with this, the market index has dropped...

Arrangements are being made for refueling by ship from Bharatpur

Kathmandu. Ships flying to Kathmandu and Pokhara from Bharatpur Airport will be able to refuel here from next week. Nepal Oil Corporation has made preparations to fill fuel here from February 6th. Deputy Director Manoj Kumar Thakur, Spokesperson o...