'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
On Thursday, the price of gold increased by Rs 5900, a huge increase in silver too
Kathmandu. The price of gold and silver has increased in the Nepali market on Thursday. According to the Federation of Nepal Gold and Silver Traders, today the price of gold has increased by Rs 5,900 per tola. Along wi...
Special discount for NMB Bank customers at Medanta Hospital in India
Kathmandu. NMB Bank has arranged a special health service discount at Medanta Hospital in India for its Visa debit and credit card holders. With this collaboration, customers can now get attractive discounts on various healthcare services at Medan...
Today, NEPSE decreased by normal numbers, turnover of 4 billion 48 crores
Kathmandu. On the third trading day of the week, NEPSE index decreased by 0.53 points to 2644.70. During the day, 18 lakh 10 thousand 106 shares of 324 companies were bought and sold, and over 4.48 billion shares were...
Demand of the transport industry from the government to implement the tax exemption continuously and uniformly
Kathmandu. The National Federation of Nepal Transport Professionals has demanded from the government to implement the 60 percent tax discount that the transport sector is getting continuously and consistently. The Federation has sent a letter to t...
Resumption of interest subsidy on subsidized loans, payment of Rs. 10.58 billion by Rashtra Bank
Kathmandu. Nepal Rastra Bank has paid 10.58 billion rupees to 50 banks and financial institutions for concessional loan interest subsidy. The government has resumed the payment of the subsidy, which was stopped due to the abuse of concessional loa...
The price of gold exceeded 3 lakh, how much is the tola?
Kathmandu. The price of gold in the Nepali market has exceeded 3 lakh per tola. The Federation of Nepal Gold and Silver Traders has fixed the price of gold at Rs 3 lakh 1 thousand 400 per tola on Friday. This is a record price.
Today, the pr...