'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months

Main News Image

Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.

"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."

Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.

mediabaaji add

Related News

National Life earned a profit of 148 million rupees in the first quarter, insurance fund close to 1 billion

Kathmandu. National Life Insurance Company Limited has earned a net profit of Rs 148 million in the first quarter of the current financial year. The company's net profit has increased by 1.81 percent compared to Rs. 13...

Abolition of excise duty on 360 items, huge increase in alcohol, junk food and energy drinks

Kathmandu. The government has made extensive changes in various tax rates through the Economic Bill 2083. Presenting the budget for the next fiscal year 2083, 84, Finance Minister Swarnim Wagle informed that the excise duty levied on 360 different...

Jan Utthan Laguvitta will not distribute dividends this year as well

Kathmandu. Jan Utthan Community Small Finance Financial Institution Limited will not distribute dividends to the shareholders from the profit of the last financial year. The meeting of the microfinance board of directors held on 26th January decid...

The price of gold increased, now how much per tola?

Kathmandu. The price of gold has increased in Nepali market today. Gold tola has gone up by 800 rupees. According to the Nepal Gold and Silver Traders Federation, gold is being traded at 284,000 rupees per tola today. Today, the price of gold per...

Watermelon farming has started for trials in the coastal area of the cyclone

Kathmandu. Bhirkot Municipality of Syangja has started watermelon farming as a test in Andhikhola coastal area.  Mayor Govinda Kumar Karmacharya said that in collaboration with Heifer International, the aim of commercial watermelon farming ha...

The government's decision to give tax exemptions to China

Kathmandu. The government has decided to provide tax exemptions for the purchase and export of necessary materials for the expansion of the second section of the ring road. With this decision, the way has been opened to proceed with the process of...