'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
What is the exchange rate of which foreign currency on Saturday?
Kathmandu. Nepal Rastra Bank has determined the foreign currency exchange rate for Saturday. According to the determined exchange rate, the buying rate of one US dollar is 146 rupees 88 paisa and the selling rate is 147 rupees 48 paisa. Similarly,...
9.43 points decline in NEPSE, turnover of 8.92 billion
Kathmandu. On the third trading day of the week, NEPSE index increased by 9.43 points to 2705.38. During the day, 201,641,883 shares of 324 companies were bought and sold, and 8,923,600,000 shares were traded. Today, while the share price of 82...
The price of gold continues to rise, how much did it reach per tola on Monday?
Kathmandu. The price of gold in the Nepalese market is constantly on the rise. Today only gold has increased by 1 thousand 900 rupees. According to the Nepal Gold and Silver Traders Federation, gold is being traded at...
Continued decline in gold prices, how much per tola on Thursday?
Kathmandu. Recently, the price of gold in the Nepalese market has been continuously falling. Gold tola decreased by 1 thousand 800 rupees. According to the Nepal Gold and Silver Business Federation, gold is being bought and sold at 292,700 rupees...
Support price of paddy: price per quintal is 36 hundred and 60 rupees
Kathmandu. The government has taken a positive decision to fix the minimum support price of paddy for the next financial year before planting paddy. The cabinet meeting held on Monday approved the proposal of the Ministry of Agriculture, Forestry...
Adding date of commercial production of hydropower projects
Kathmandu. The Nepal Electricity Authority has prepared to add RCOD to the final date for starting commercial production of hydropower projects that have not been able to start commercial production due to various reasons despite the PPA.
Th...