'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
Solu Hydropower's IPO is being distributed today, how many will get shares?
Kathmandu. The IPO of Solu Hydropower Limited will be distributed today. Nabil Investment Banking Limited and Himalayan Capital Limited will distribute the IPO today at 3:30 PM as the company's securities issuing and sales managers.
In the c...
The number of candidates opening accounts in banks and financial institutions is increasing
Kathmandu. After the Election Commission mandated that election expenses should be paid through bank and financial institution accounts, candidates opened accounts in a hurry. The Commission has arranged for political parties and candidates to ope...
What is the exchange rate of foreign currency, which currency?
Kathmandu. Nepal Rastra Bank has determined the foreign currency exchange rate for Monday. According to the new rates published by the Central Bank, the buying rate of one US dollar has remained at 154 rupees 21 paise and the selling rate ha...
All preparations for financial calculations are complete
Kathmandu. The preparations for the second economic calculation have reached the final stage. The National Statistics Office said that enumerators and necessary inspectors have been circulated throughout the country and have reached the relevant a...
Stock markets rose by double digits, greener on Bikas Bank and Hydropower indices
Kathmandu. On the third day of the week, i.e. Tuesday, the stock market has increased by double digits. Today, the NEPSE index increased by 13.51 points to 2812.34 points. In the stock market today, 348,520,000 shares of 340 companies of various s...
Foreign Currency Exchange Rates: What are the rates for Dollars, Euros and Pounds?
Kathmandu. Nepal Rastra Bank has determined the official exchange rate of foreign currency for today. According to the Central Bank, today the buying rate of Indian rupees 100 is fixed at 160 rupees and the selling rate of 160 rupees is 15 paise....