'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months

Main News Image

Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.

"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."

Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.

mediabaaji add

Related News

An increase of 16.67 points in NEPSE, the turnover is limited to 2.79 billion

Kathmandu. On Sunday, the last trading day before Tihar, the stock market NEPSE index rose by 16.67 points to 2503.85. 6.199 thousand shares of 323 companies were bought and sold in NEPSE on this day, with a turnover o...

Moving towards the construction of 1200 MW Budhigandaki hydropower project

Kathmandu. The Budhigandaki hydropower project with a capacity of 1200 MW has progressed towards the construction stage. With the agreement between the Ministry of Finance and the National Planning Commission on the investment framework of this pr...

Nepal's public debt for the first time reached 30 trillion, 45.59 percent of GDP!

Kathmandu. The total public debt of Nepal has exceeded 30 trillion rupees for the first time. According to the Public Debt Management Office, the total public debt of the government has reached Rs. This is 45.59 percent of GDP.

By the end of...

Cancel the contract of the builder who does not work on time

Kathmandu. The Khajura rural municipality of Banke has canceled the contract of the builder who did not complete the project on time. Dil Bahadur Paudel, Chief Administrative Officer of Khajura Rural Municipality, informed that the progress of the...

What is the exchange rate of which foreign currency on Tuesday?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the fixed exchange rate, the buying rate of one US dollar is 147 rupees 43 paisa and the selling rate is 148 rupees 3 paisa. The buying rate...

Trial of Tamghas-Burtibang 132 KV transmission line started

Kathmandu. The testing of the 132 kV double circuit transmission line constructed by the Nepal Electricity Authority from Gulmi headquarters Tamghas to Burtibang has been started from today. The line built under Burtibang-Paudiamrai-Tamghas-Sandhi...