'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months

Main News Image

Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.

"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."

Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.

mediabaaji add

Related News

Solu Hydropower IPO to issue from today

Kathmandu. Solu Hydropower Limited has issued an initial public issue IPO for the local residents of the project-affected areas and Nepali workers who are employed abroad from today on November 7th. The company was all...

The euro and pound fell, while the Australian dollar and Bahraini dinar rose

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currencies for Friday. Today, while the exchange rate of the US dollar and the Kuwaiti dinar remained stable, currencies including the Bahraini dinar and the Australian dolla...

Rastra Bank is issuing 20 billion rupees bonds today

Kathmandu. Nepal Rastra Bank is going to issue bonds worth 20 billion rupees again today on January 23rd. The Central Bank is going to issue 'Nepal Rastra Bank Bond 2083 E' today. This bond will be discussed online till 2 pm today. The interest ra...

The decision of the Water Industry Federation to increase the price of drinking water

Kathmandu. Nepal Water Industry Federation has decided to increase the price of treated drinking water. According to the federation, the increase in the price of raw materials and the increase in transportation costs have made it impossible to ope...

What is the exchange rate of which foreign currency on Thursday?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to Rashtra Bank, the buying rate of one US dollar has been fixed at 145 rupees 22 paisa and the selling rate is 145 rupees 82 paisa. Similarly,...

The price of gold and silver decreased, how much is the transaction per tola?

Kathmandu. Today, the price of gold and silver in the local market has fallen somewhat. Compared to Thursday, the price of both has decreased. According to the Federation of Nepal Gold and Silver Traders, today the price of one tola of gold is Rs...