Muglin -Malekhu road upgradation work started

Main News Image

Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.

According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.

According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.

This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.

mediabaaji add

Related News

Here is the foreign currency exchange rate for today

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the National Bank, the buying rate of one US dollar has been fixed at 151 rupees 66 paisa and the selling rate is 152 rupees 26 paisa.

...

The Australian dollar, euro and pound fell, while the Bahraini dinar rose

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currencies for Monday. Even today, the US dollar remains at a high value. Some currencies, including the Bahraini dinar, have appreciated. According to Nepal Rastra Bank, the...

NEPSE increased by 7.66 points throughout the week, how much is the transaction on which day?

Kathmandu. This week, NEPSE index increased by 7.66 points to 2615.03 points. NEPSE, which closed last week at 2607.37 points, increased by 7.66 points to reach 2615.03 points this week. The market was open on all five trading days this week. This...

The supply of cooking gas will be eased within a few days, the ministry's request to avoid hoarding

Kathmandu. The Ministry of Industry, Commerce and Supply has said that the supply of LP gas for cooking in the market will be eased within a few days. In a statement released on Tuesday by the spokesperson of the ministry, Netra Prasad Subedi, it...

NEPSE decreased by 13 points, turnover exceeded 5 billion!

Kathmandu. On the fourth trading day of the week, the NEPSE index fell by 13.35 points to 2635.94 points. Today, when 1.6 million shares of 323 companies were bought and sold, the total turnover reached 5.17 billion rupees.

In trading, the s...

A significant increase in the import of petroleum products

Parsa. In the six months of the current financial year, petroleum products worth Rs 90 billion and six crores have been imported through Birgunj. During the same period of the current year, petroleum products worth Rs. In the six months of the cur...