Muglin -Malekhu road upgradation work started

Main News Image

Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.

According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.

According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.

This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.

mediabaaji add

Related News

The government will give Rs 15,000 each to the victims of the Genji movement

Kathmandu. The government has decided to give a relief of Rs 15,000 each to the injured of the Janeji movement. Jagdish Kharel, Government Spokesperson and Minister of Communication and Information Technology informed...

Young farmer's strawberry farming in Dang flourishing, business worth lakhs

Kathmandu. Due to agricultural technology and professional thinking, strawberry cultivation has started to flourish in Ghorahi area of ​​Dang. Dasharath Saud, 27 years old from Kailali, has been doing business of lakhs from his strawberry farm on...

Yoyo Plywood Industry of Kohalpur closed, more than 600 workers unemployed

left Yoyo Plywood Industries Pvt Ltd located in Kohalpur Municipality-14 of Banke has been closed for the last three months and more than 600 workers working there have become jobless. The workers' jobs were taken away...

Hydropower projects in Myagdi were affected by flood and landslides, production of 20 megawatts of electricity was stopped

Myagdi. Due to floods and landslides, the work of the hydropower project under construction in Myagdi has been affected, while the power generation from two projects that are in operation has stopped. The projects of Dhawalagiri, Annapurna and Mal...

125 contracts stopped due to fuel price hike

Chitwan. 125 contract works run by Infrastructure Development Office Chitwan have come to a halt. Due to the rising cost of essential items including fuel, it has become impossible to work on these contracts. According to the head of the office, B...

What is the exchange rate of foreign currency on Wednesday?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to Rashtra Bank, today the buying rate of one US dollar has remained at 141 rupees 42 paisa and the selling rate ha...