Muglin -Malekhu road upgradation work started

Main News Image

Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.

According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.

According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.

This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.

mediabaaji add

Related News

Historic Free Trade Agreement between India and New Zealand

Kathmandu. A new chapter has started in the bilateral trade relations between India and New Zealand from Monday. The two countries have signed a historic free trade agreement. With the agreement, it is expected to bring radical changes in the fiel...

The government does not listen to the warning of IT professionals that the digital economy will be lost

Kathmandu. Professionals in the information technology and software services sector have requested the government to give high priority to the IT industry through the budget of the next financial year 2083 and 84.

The pre-budget recommendati...

The government will give Rs 15,000 each to the victims of the Genji movement

Kathmandu. The government has decided to give a relief of Rs 15,000 each to the injured of the Janeji movement. Jagdish Kharel, Government Spokesperson and Minister of Communication and Information Technology informed...

What is the exchange rate of which foreign currency on Sunday?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the fixed exchange rate, the buying rate of one US dollar is 143 rupees 97 paisa and the selling rate is 144 rupees 57 paisa. Similarly, the...

The exchange rate of foreign currency exceeds 153 rupees in the US dollar, how much more?

Kathmandu. Nepal Rastra Bank has published the official exchange rate of foreign currency for today. According to the Central Bank, today the buying rate of one US dollar is 153 rupees 16 paisa and the selling rate is 153 rupees 76 paisa.

Si...

Vehicles are running on Nagadhunga tunnel from today: Nepal is entering the tunnel age

Kathmandu. The dream of the Nepalese people for years to run vehicles in the tunnel has finally been realized. The much-awaited Nagadhunga tunnel, which was built on November 14, 2019, has been formally opened for traffic from Monday.

The sp...