Muglin -Malekhu road upgradation work started

Main News Image

Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.

According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.

According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.

This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.

mediabaaji add

Related News

2 million shares of Bhujung Hydropower IPO coming

Kathmandu. Nepal Securities Board Sebon has given permission to Bhujung Hydropower Limited to issue an initial public issue IPO to the general public. Sebon has given approval to the company to issue 2 million shares w...

China's national highway to Kerung opens, 16 dead and 546 missing

The Kathmandu. Chinese technical and rescue teams have stepped up efforts to reopen a major national highway leading to the port of Kerung in the Tibet Autonomous Region, which has been damaged by a flood caused by a glacier burst in the high moun...

The exchange rate of foreign currency, the dollar crossed 152 rupees

Kathmandu.  Nepal Rastra Bank has determined the official exchange rate of foreign currency for Wednesday. According to the Central Bank, today the buying rate of one US dollar is 152 rupees 31 paisa and the selling rate is 152 rupees 91 pais...

Apollo Hydropower opens first phase IPO sale from tomorrow

Kathmandu. Apollo Hydropower Limited is going to issue IPO from tomorrow, February 11th. The company is going to issue an IPO in the first phase tomorrow for the local residents of the project-affected areas and Nepalis working abroad.

The N...

Farmers line up overnight to sell paddy, rush to government procurement centre

Kailali.  Swaroop Chaudhary from Ghodaghodi Municipality-3 here went to Bhajani to sell paddy early on Saturday morning. After the government started buying paddy by fixing the support price of paddy, the sub-centre of the Food Management and...

Revenue collection of 21 lakh 10 thousand in one day in traffic action

Kathmandu. In the past 24 hours, two thousand 102 motorists have been prosecuted for violating traffic rules. From this, the revenue of Rs 21 lakh 10 thousand 514 has been deposited in the state treasury. According to the Kathmandu Valley Traffic...