Muglin -Malekhu road upgradation work started

Main News Image

Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.

According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.

According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.

This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.

mediabaaji add

Related News

The price of eggs increased, the farmers still did not get the cost price

Kathmandu. The price of eggs, which has fallen due to the effect of bird flu, has started to rise. After production decreased and demand increased, prices started to rise. Nepal Layers Poultry Farmers Association decides the market price by taking...

NEPSE increased by 7.66 points throughout the week, how much is the transaction on which day?

Kathmandu. This week, NEPSE index increased by 7.66 points to 2615.03 points. NEPSE, which closed last week at 2607.37 points, increased by 7.66 points to reach 2615.03 points this week. The market was open on all five trading days this week. This...

166 entities allowed to mine 16 types of minerals

Kathmandu. The Department of Mines and Geology has granted permission for the mining of 16 different types of minerals. According to the department, permission was given with the aim of supporting industrial production and economic growth by devel...

Import of 31 billion through Rasuwagadhi crossing, export of dry grass from Nepal

Kathmandu. In the nine months of the current financial year, goods worth Rs. 31 billion 30 million have entered through Rasuwagadhi, an important point of trade between Nepal and China. Among the materials imported through the border are roll clot...

The price of the American dollar is the highest so far, how much is one dollar Nepalese rupee?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for Saturday today. According to the fixed exchange rate, the value of the US dollar has reached its highest point so far. The buying r...

Asset confiscation, bank account freezing and foreign travel ban if the co-operative fund is not returned

Kathmandu. To make the cooperative sector more orderly, transparent and accountable, the government has brought forward a new process through the bill. The government passed the Cooperatives First Amendment Bill, 2083 in the House of Representativ...