Muglin -Malekhu road upgradation work started

Main News Image

Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.

According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.

According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.

This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.

mediabaaji add

Related News

The government will give 25,000 per family displaced from the river banks of the valley

Kathmandu. The government has decided to provide a lump sum of Rs 25,000 as a relief to the families who will be displaced after the removal of hazardous settlements on the banks of various rivers in Kathmandu Valley. The cabinet meeting held at S...

Solu Hydropower will issue IPO from November 7th

Kathmandu. Solu Hydropower Limited is going to issue the first phase of IPO for the local residents affected by the project and the Nepalese who have gone for foreign employment from the coming 7th of November. The company has received permission...

NEPSE increased by 35.05 points throughout the week, how much is the transaction on which day?

Kathmandu. This week, NEPSE index increased by 35.05 points to 2620.92 points. NEPSE, which closed at 2585.87 points last week, increased by 35.05 points to 2620.92 points this week. The market was open for four trading days this week. In which NE...

National Life earned a profit of 148 million rupees in the first quarter, insurance fund close to 1 billion

Kathmandu. National Life Insurance Company Limited has earned a net profit of Rs 148 million in the first quarter of the current financial year. The company's net profit has increased by 1.81 percent compared to Rs. 13...

Genji Movement: Payment of over five billion claims for physical and other damages

Kathmandu. Out of the insurance claims for physical and other damages during the Zenji movement, Rs. 5.18 billion has been paid to the insured so far. The Nepal Insurance Authority issued a press release today and said that out of a total of 3,303...

A huge increase in the price of gold, how much is the transaction?

Kathmandu. Compared to Thursday, the price of gold has increased significantly. 3,500 per gold tola and the price of silver of the same amount has increased by Rs. According to the Federation of Nepal Gold and Silver T...