Muglin -Malekhu road upgradation work started

Main News Image

Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.

According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.

According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.

This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.

mediabaaji add

Related News

Naima's request to the government - automobile sector should be recognized as a 'necessity' and not a 'luxury'

Kathmandu. The delegation headed by Ritu Singh Vaidya, President of Nepal Automobile Importers and Manufacturers Association Naima, Finance Minister Dr. Swarnim Wagle met with and presented detailed suggestions for policy and systemic reforms rela...

Money Laundering Act has been amended to prevent complaints from becoming a weapon: Finance Minister Wagle

Kathmandu. The government has amended the controversial provision made through an ordinance in the Prevention of Asset Laundering and Money Laundering Act and returned it to the old legal system. Finance Minister Dr. Swarnim Wagle has said that so...

Drop in gold prices, how much per tola on Tuesday?

Kathmandu. There has been a huge fall in the price of gold in the Nepalese market. Today, gold has fallen by 3,800 rupees per tola. According to the Nepal Gold and Silver Traders Federation, gold has been fixed at Rs 2...

As the price of gold and silver continues to rise, how much has it reached per tola today?

Kathmandu. The price of gold has increased in the Nepali market on Sunday. According to the Federation of Nepal Gold and Silver Dealers, compared to Friday, the price of gold tola has increased by 2800 rupees and has remained at 270 thousand 60...

Gold and silver prices are at an all-time high

Kathmandu. On Monday, the price of both gold and silver was the highest ever. The Nepal Gold and Silver Business Federation has fixed the price of gold at 261,700 rupees per tola on this day. Which price is 3 thousand 400 rupees more than the prev...

Suryakund Hydro's IPO allotment, 57 thousand 243 people got shares

Kathmandu. Suryakund Hydro Electric Limited has issued an IPO to the general public. Sales manager Kumari Capital Limited has allotted the IPO this morning. This company had opened the IPO sale of 5 lakh 72 thousand 431 shares with a face value of...