Electricity generation started from Setikhola project
Kaski. Setikhola hydropower project of 22 megawatt capacity, completed in Pokhara Metropolitan City-33 of Kaski, has started generating electricity. The project promoted by Seti Khola Hydropower Limited started in December 2078.
After the inspection and testing of the project by the technical team of the Nepal Electricity Authority, the produced electricity has started to flow in the national transmission system as a test, according to Deepak Baral, the director of the promoter company.
According to him, initially 15 days will be in the project trial period. After that, regular commercial production will begin. During that period, the electricity produced will be transferred to the Nepal Electricity Authority's system, while technical testing of the project and equipment will be conducted.
Express
Related News
IPO allocation of Bhujung Hydropower, 83 thousand got shares
Kathmandu. Bhujung Hydropower Limited has completed its IPO allotment to the general public. Sales manager Kumari Capital Limited has allotted the IPO today at 9 am on Tuesday. The company issued a total of 830,000 IPO shares to the general public...
What is the new exchange rate for foreign currencies, US dollars and pounds?
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the new rate issued by the Central Bank, today the buying rate of one US dollar is 154 rupees 02 paisa and the selling rate is 154 rupees 62...
Construction of two hydropower projects of 84 megawatt capacity in Rahughat of Myagdi has been completed
Kathmandu. Tundi Power Company has simultaneously constructed two hydropower projects on the Rahughat River that flows through Raghuganga Rural Municipality of Myagdi. Ghuganga Rural Municipality-4, 7 and 8 Ward No. 4, 7 and 8 of the two projects...
Shangrila Development Bank declares 10 percent dividend
Kathmandu. The meeting of the board of directors of Sangrila Development Bank Limited held on the afternoon of 28th October has announced the dividend to the shareholders.
The meeting has announced that 5% bonus s...
Four construction companies blacklisted, not allowed to participate in government contracts
Kathmandu. The Public Procurement Monitoring Office has blacklisted four construction businessmen and joint venture JVs based on the recommendations of various public bodies. The office has informed that according to sub-section 1 of section 63 of...
What is the foreign currency exchange rate in dollars, euros and pounds?
Kathmandu. Nepal Rastra Bank has published the official exchange rate of foreign currencies for today. According to the new rate determined by the Central Bank, today the buying rate of one US dollar is 152 rupees 60 paisa and the selling rate is...