Electricity generation started from Setikhola project

Main News Image

Kaski. Setikhola hydropower project of 22 megawatt capacity, completed in Pokhara Metropolitan City-33 of Kaski, has started generating electricity. The project promoted by Seti Khola Hydropower Limited started in December 2078.

After the inspection and testing of the project by the technical team of the Nepal Electricity Authority, the produced electricity has started to flow in the national transmission system as a test, according to Deepak Baral, the director of the promoter company.

According to him, initially 15 days will be in the project trial period. After that, regular commercial production will begin. During that period, the electricity produced will be transferred to the Nepal Electricity Authority's system, while technical testing of the project and equipment will be conducted.

mediabaaji add

Related News

The price of gold and silver decreased, how much per tola?

Kathmandu. On Thursday, the price of gold and silver decreased in the Nepalese market. According to the Federation of Nepal Gold and Silver Traders, today the price of gold has decreased by 800 rupees per tola. Along w...

Four construction companies blacklisted, not allowed to participate in government contracts

Kathmandu. The Public Procurement Monitoring Office has blacklisted four construction businessmen and joint venture JVs based on the recommendations of various public bodies. The office has informed that according to sub-section 1 of section 63 of...

Foreign Currency Exchange Rate: Selling rate of US dollar remained at 152 rupees 94 paise

Kathmandu. Nepal Rastra Bank has determined the official exchange rate of foreign currency for today. According to the latest information published by the Central Bank, the buying rate of one US dollar, which is becoming stronger in the internatio...

Electricity of Bheri-Babai project will be connected to national transmission: 132 kV transmission line is being constructed

Surkhet. The process of connecting the electricity produced by the national pride Bheri-Babai diversion multi-purpose project to the national transmission system has started.

In order to connect the electricity produced by the project to the...

Double-digit growth in NEPSE, turnover limited to 3 billion 29 million

Kathmandu. On the second trading day of the week, the NEPSE index increased by 16.37 points to 2619.99. During the day, 78 lakh 4 thousand 45 shares of 325 companies were bought and sold, and 3 billion 294 million shar...

3 billion 55 crores damage to agriculture and livestock sector across the country due to rain

Kathmandu. The Ministry of Agriculture and Livestock Development has said that due to the heavy rains that occurred last October, there was a loss of 3.55 billion in the fields of agriculture and animal husbandry acros...