Kaski. Setikhola hydropower project of 22 megawatt capacity, completed in Pokhara Metropolitan City-33 of Kaski, has started generating electricity. The project promoted by Seti Khola Hydropower Limited started in December 2078.
After the inspection and testing of the project by the technical team of the Nepal Electricity Authority, the produced electricity has started to flow in the national transmission system as a test, according to Deepak Baral, the director of the promoter company.
According to him, initially 15 days will be in the project trial period. After that, regular commercial production will begin. During that period, the electricity produced will be transferred to the Nepal Electricity Authority's system, while technical testing of the project and equipment will be conducted.
Express
Related News
Heavy fall in the price of gold and silver, how much is the transaction going on today?
Kathmandu. On Tuesday, the price of gold and silver, which is constantly increasing, has fallen sharply. According to the Nepal Gold and Silver Traders Federation, today the price of gold has decreased by 7 thousand 900 rupees per tola.
Alon...
BP highway reconstruction is accelerated, 3.2 km road will be constructed through JICA for 2.6 billion
Ramechhap. The remaining road section of the Kavre-Sindhuli section from Piple in Kavre to Barkhekhola in Sindhuli will be constructed in two lanes with the support of Japan International Cooperation Agency (JICA).
Suman Yogesh, Head of Road...
17.53 points decline in NEPSE, turnover above 14.56 billion
Kathmandu. On the fifth trading day of the week, NEPSE index decreased by 17.53 points and remained at 2714.05. During the day, 354 million 77 thousand 939 shares of 320 companies were bought and sold, with a turnover of 14.56 billion 31 million s...
Genji Movement: Payment of over five billion claims for physical and other damages
Kathmandu. Out of the insurance claims for physical and other damages during the Zenji movement, Rs. 5.18 billion has been paid to the insured so far. The Nepal Insurance Authority issued a press release today and said that out of a total of 3,303...
Solu Hydropower's IPO will be distributed next week
Kathmandu. The IPO of Solu Hydropower Limited will be distributed only next week. Nabil Investment Banking Limited and Himalayan Capital Limited as sales managers have informed that they are working to distribute the IPO only.
In the company...
4 points of agreement between the agitating sugarcane farmers and industrialists in Sarlahi, to be paid within a month
Surlahi. A four-point agreement has been reached between the farmers and the industrial side, who are on a dharna demanding the arrears of sugarcane sold to the Annapurna sugar industry in Dhankaul, Sarlahi. On the ini...