8 billion spent on the north-south road, black paper target up to Korla
Kathmandu. As part of the north-south trade route expansion project, Rs. The project has spent 82 percent of the budget while the proposed cost estimate of the project is Rs 10.57 billion till FY 2081-82.
Under the Korla road of national pride connecting India and China, a 202 km road track has been opened from Maludhunga in the mountain to Nepal-China Korlana. According to the decision of the Council of Ministers on November 12, 2073, Kaligand Corridor 9Beni-Jomsam-Korla road was established as a separate project. Under which the project has been continuously upgrading the roads in Parbat, Myagdi and Mustang sections since 2073 and 74. The last revised completion period of the project has been proposed for the year 2082 and 2083. But since the road up to Korlanaka needs to be paved, it is certain that the completed period will be revised again.
Under this Kaligandaki Corridor road project, the target is to open 202 km of road tracks, 97 km of road gravel, 150 km of tarmac and 19 bridges. According to the target, by the year 2081 and 2082, the project has opened 202 kilometers of road tracks, 94 kilometers of road gravel, 88 kilometers of black paper and construction of 14 bridges have been completed, project chief Tejashwi Sharma has informed.
For Korla road, through the project, 3 km of gravel and 10 km of Kagbeni-Chusang will have to be blacked on 27 km of the road and a new contract will have to be issued for the rest. Under this project, if the 9 Kagbeni-Korla road section is also covered with black, the total cost estimate of the project may be more than 15 billion, according to the head of the project Sharma. According to the head of the project, the goal is to upgrade the road and blacken the entire 202 km double lane of the Korla road section and build the necessary bridge.
Express
Related News
The price of gold and silver fell, the price of gold continued to fall again
Kathmandu. Today the price of gold has decreased. According to the Federation of Nepal Gold and Silver Traders, the price of gold decreased by 1500 rupees per tola to 3400 rupees today. The price of gold has been falling continuously since last Mo...
This week, NEPSE has decreased by normal numbers, how much is the transaction on which day?
Kathmandu. This week, NEPSE index decreased by 0.56 points and reached 2714.05 points. NEPSE, which closed at 2714.61 points last week, decreased by 73.18 points to 2714.05 points this week. The market was open for five trading days this week. In...
The price of the US dollar exceeded 152 rupees, how many other currencies?
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the fixed exchange rate, the buying rate of one US dollar is 151 rupees 56 paisa and the selling rate is 152 rupees 16 paisa. Similarly, the...
The fuel facility of certain officials and government employees has been reduced
Kathmandu. In order to control public expenditure and manage the fuel crisis, the government has decided to significantly reduce the fuel facilities provided to government employees and special officials. According to the Ministry of Finance, due...
Courage Energy and NRN Infrastructure have applied to the Securities and Exchange Board to issue 100 percent rights.
Kathmandu. Two companies have sought permission from the Nepal Securities Board to issue rights. Courage Urja Limited and NRN Infrastructure Development Limited have applied to the board demanding issuance of rightful shares at 100 percent rate.&n...
Farmers are dissatisfied with the support price of wheat, complaining that even the cost does not rise
Kathmandu. Farmers have expressed dissatisfaction with the support price of wheat set by the government. Although the government has fixed the support price of wheat at Rs 3,945 per quintal this year, the farmers complain that the price does not e...