8 billion spent on the north-south road, black paper target up to Korla

Main News Image

Kathmandu. As part of the north-south trade route expansion project, Rs. The project has spent 82 percent of the budget while the proposed cost estimate of the project is Rs 10.57 billion till FY 2081-82.

Under the Korla road of national pride connecting India and China, a 202 km road track has been opened from Maludhunga in the mountain to Nepal-China Korlana. According to the decision of the Council of Ministers on November 12, 2073, Kaligand Corridor 9Beni-Jomsam-Korla road was established as a separate project. Under which the project has been continuously upgrading the roads in Parbat, Myagdi and Mustang sections since 2073 and 74. The last revised completion period of the project has been proposed for the year 2082 and 2083. But since the road up to Korlanaka needs to be paved, it is certain that the completed period will be revised again.

Under this Kaligandaki Corridor road project, the target is to open 202 km of road tracks, 97 km of road gravel, 150 km of tarmac and 19 bridges. According to the target, by the year 2081 and 2082, the project has opened 202 kilometers of road tracks, 94 kilometers of road gravel, 88 kilometers of black paper and construction of 14 bridges have been completed, project chief Tejashwi Sharma has informed.

For Korla road, through the project, 3 km of gravel and 10 km of Kagbeni-Chusang will have to be blacked on 27 km of the road and a new contract will have to be issued for the rest. Under this project, if the 9 Kagbeni-Korla road section is also covered with black, the total cost estimate of the project may be more than 15 billion, according to the head of the project Sharma. According to the head of the project, the goal is to upgrade the road and blacken the entire 202 km double lane of the Korla road section and build the necessary bridge.

mediabaaji add

Related News

The price of the American dollar is the highest so far, how much is one dollar Nepalese rupee?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for Saturday today. According to the fixed exchange rate, the value of the US dollar has reached its highest point so far. The buying r...

The value of the US dollar is at an all-time high

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the fixed exchange rate, the value of the US dollar has risen to its highest point so far. According to the fixe...

IPO sale of Bhujung Hydropower is open, how many shares can be filled?

Kathmandu. Bhujung Hydropower Limited has opened the IPO sale for the public from January 12 today. The company has issued the IPO and distributed it to local residents affected by the project and Nepalese who have gone abroad for employment, and...

Tortoise speed of budget implementation in Karnali Province: Development expenditure under 20% in 8 months

Surkhet. Even though the Karnali state government has passed the two quarter period of the current financial year, it has not been able to show encouraging results in the implementation of the budget. After the end of 8 months of February of the f...

Solu Hydropower's IPO Local allotment

Kathmandu. Solu Hydropower Limited has distributed 10 million IPO shares issued for project-affected locals today. The allotment of 1 million shares of the company's foreign employment has already been completed.

After the completion of the...

What is the exchange rate of which foreign currency on Wednesday?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the fixed exchange rate, the buying rate of one US dollar is 147 rupees 50 paisa and the selling rate is 148 rupees 10 paisa.

Similarly...