'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months

Main News Image

Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.

"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."

Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.

mediabaaji add

Related News

MDRT honor and training program of National Life completed

Kathmandu. National Life Insurance Company Ltd. has completed the MDRT honor and training program under the chairmanship of Chief Hospitality and Chief Executive Officer Mrs. Prema Rajya Lakshmi Singh, President of the company at Dushit Thani Hima...

Due to lack of cooking gas in the market, the corporation started sales and distribution from the central office

Kathmandu. After increasing complaints about lack of cooking gas LPG in the market, Nepal Oil Corporation has started sales and distribution of gas for general public from its central office in Teku. After receiving continuous complaints from the...

Vehicles are running on Nagadhunga tunnel from today: Nepal is entering the tunnel age

Kathmandu. The dream of the Nepalese people for years to run vehicles in the tunnel has finally been realized. The much-awaited Nagadhunga tunnel, which was built on November 14, 2019, has been formally opened for traffic from Monday.

The sp...

Import of petroleum products worth four billion 48 crores from Kankarbhitt

Bhadrapur. In the first quarter of the current fiscal year 2082 and 083, petroleum products worth four billion 48444568 thousand have been imported from Kankarvitta through the eastern border. Petrol, diesel, LP gas, ATF, kerosene have been import...

Parliamentary committee directive to government to implement tracking system on gas cylinders

Kathmandu. The Committee on Industry and Commerce and Labor and Consumer Affairs of the House of Representatives has instructed the government to use modern technology and implement an effective tracking system for the consumption, management and...

Question to the Minister of Finance: What source of income did you see and are you going to increase the salary of the employees?

Rusha Thapa

Kathmandu. More than five years have passed since cooperatives, microfinance, and finance collapsed. Now the crisis has started to appear in the bank as well. It has been the same time that the country has been in economic recess...