'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months

Main News Image

Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.

"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."

Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.

mediabaaji add

Related News

What is the former king in India doing in the discussion for more than a week on the security of the governor?

Kathmandu. Former King Gyanendra Shah is currently in India. The former king, who is in Siliguri, India, reached Siliguri via Damak on 2nd of January. There is no indication that Purvaraja will return in 1-2 days. It is not clear how long the form...

The price of gold and silver decreased, how much per tola?

Kathmandu. On Thursday, the price of gold and silver decreased in the Nepalese market. According to the Federation of Nepal Gold and Silver Traders, today the price of gold has decreased by 800 rupees per tola. Along w...

Hotel Park Land has applied to the Securities and Exchange Board for an IPO issue

Kathmandu. Hotel Park Land Limited has applied to the Securities Board for permission to issue IPO. The company has sought permission from the board to issue a total of 1.5 million shares at a marked rate of Rs 100 per share. 

Citizens...

Naima's interest in EV motor capacity dispute, urges government to make clear standards

Kathmandu. Nepal Automobile Importers and Manufacturers Association Naima has said that it has drawn attention to the recent comments, discussions and explanations regarding the motor capacity of electric vehicles 9EV0.

Naima issued a statem...

The tenth amendment of the National Bank Act 2058

Kathmandu. The Ministry of Finance has started the process of amending the existing legal structure related to Nepal Rastra Bank. The ministry has released the draft of the bill to amend the Nepal Rastra Bank Act, 2058 and has sought opinions and...

What is the exchange rate of which foreign currency on Monday?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the fixed exchange rate for today, the buying rate of one US dollar is 142 rupees 54 paisa and the selling rate is 143 rupees 14 paisa. The b...