'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
Financial management of Tila 1 hydropower project led by NMB Bank
Kathmandu. NMB Bank Limited has successfully completed the financial management as the lead bank for the Tila 1 Hydropower Project located in Calikot district with a capacity of 440 MW according to the production permit. Promoted by SC Power Compa...
Solu Hydropower's IPO sale is open to the general public from today
Kathmandu. Solu Hydropower has opened the IPO sale for the general public from January 29th today. On October 24th, the company received permission from the Nepal Securities Board to issue 20 million ordinary shares worth Rs 2 billion at Rs 100 pe...
What is the exchange rate of which foreign currency for Tuesday?
Kathmandu. Nepal Rastra Bank has determined the foreign currency exchange rate for Tuesday. According to Rashtra Bank, the buying rate of one US dollar has been fixed at 142 rupees 48 paisa and the selling rate is 143...
From now on, when the airline's aircraft are diverted, they will land at Bhairahawa
Kathmandu. In the event that Nepal Airlines Corporation planes could not land at Tribhuvan International Airport due to various reasons, now Gautam Budh International Airport will be used. Spokesperson Anil Ghimire inf...
Unseasonal rain in Morang has reduced paddy production, farmers are worried
Morang. In terms of rice production, Morang district, which is considered to be the best in the country, has seen a decrease in rice production this year due to unseasonal rains. Compared to last year, the production o...
Monthly stipend for the injured of Gen-G movement: Govt started four tier classification
Kathmandu. The government has accelerated the classification of those who were injured during the demonstration by Yuva Pusta Genji on August 23 and 24. The Ministry of Home Affairs has implemented the procedure approved by the Council of Minister...